“You’ve heard of building a ship in a bottle? Well this was building a crane in a cement box!” – KEL Project Coordinator

When it comes to installing a customers crane, we at Kristian Electric are the best at what we do. Even though each crane order is unique, the steps to manufacture and install each piece can be somewhat routine. However, in January of 2013, we were tasked with a crane installation that would have made MacGyver proud.

A construction company approached us to install a Gorbel workstation crane in a city pump station. The crane would be used for maintenance and repairs on the pumps, motors and valves in the lower level of the water lift station. Easy peezy right? Wrong.

The room the crane needed to be installed in was no more than a few feet larger than the workstation crane itself, and with dimensions of 20’ – 5″ headers and 43’ – 6″ long runways, this left little room for anything else. (Fig.1) Another obstacle to consider was building access, as the largest entrance to the building was a double man door.

So not only did KEL technicians need to ensure safety for themselves, working in such a confined environment but for the crane components as well, all while completing the job in a timely manner. “We had a number of obstacles to overcome before we even started that required a lot of forethought and measuring.” says the Kristian Electric project coordinator on the job.

After putting many heads together, a plan was formed. To begin with, the general contractor, removed all of the old equipment and piping from the pump station. Then, with the use of a KEL rental electric chain hoist installed on the existing monorail (Fig.2), a special spreader beam was engineered and fabricated to lift and lower a spyder crane, with only 2″ of clearance, through the man door and into the room. (Fig.3)

Meanwhile, a picker truck was situated outside the building. (Fig.6 The picker, in conjunction with the spyder crane were used to feed one of the headers through a window from outside as it needed to be installed above the monorail beam.

Then KEL techs went to work constructing the workstation crane in their little tin can using the monorail hoist to lower components into the room (Fig.5) and the spyder crane to hoist them into place. (Fig.6,7) Once completed, the spyder crane was disassembled and hoisted out of the room using the monorail. (Fig.8) The chain hoist was removed and voila!

All said and done, the job took a little over a week. Everything went as expected and our customer was very pleased. So, just like MacGyver always said; ‘any problem can be solved, with a little ingenuity’ (and a little KEL).

The Miller Venture 150 S Battery Powered Welder

Welding Without Cords? Now You Can. The future of off-grid welding is here — and it’s powerful. Meet the Miller Venture 150 S — a fully battery-powered stick and TIG welder that delivers serious performance without a single cord, generator, or compromise. This...

Demag Parts and Service Canada | Used Cranes & OEM Support

If you’re searching for trusted Demag parts and service in Canada, you’ve come to the right place. At Kristian Electric, we know Demag gear is built to last — and we’re here to keep it running like new. At Kristian Electric Ltd., we’re proud to be your authorized...

Gearing Up the Next Generation

More Than Helmets — Real Support, Real Service, and the Right Equipment Welding students deserve gear that works as hard as they do. At Kristian Electric, we’ve been supporting Canadian welders since 1964 — and that includes the students learning the trade today....